OFFICE DESIGN-BUILD PROJECT
Graphic Packaging
Tustin, California
Halo Electric delivered a design-build electrical upgrade for Graphic Packaging in Tustin, supplying full engineering and permits. The project combined new power distribution and HVAC equipment connections with an office lighting retrofit, installing 120 new LED fixtures to replace outdated fluorescent lighting.
PROJECT SCOPE
- Design-build electrical work, including full engineering and permits
- New 30 kVA transformer
- New 480V distribution panel and 120/208V panel
- Power for six rooftop condensers and six interior fan coils
- 120 new LED fixtures replacing outdated fluorescent lighting
- SECTOR
- Office
- COMPLETED
- PROJECT SCHEDULE
- Eight weeks · Early September–October 2026
- CONTRACTOR
- Halo Electric Company Inc.